Off the grid, and never off.
Grid congestion means no connection in this part of Barneveld for years to come. The hall had to run anyway. Solar, a 2 MWh battery and Wattmaestro control keep it sorting eggs around the clock.
THE IMPACT
0
Grid connection
2MWh
Battery storage on site
24/7
Own energy production
No connection,
no time to wait.
In Barneveld a new hall was built for sorting, packing and shipping eggs. Energy intensive work that runs continuously, at an average of 3 MWh a day. Grid congestion in the region means no connection will be available for years. For most installers that is where a project stops. No safety net at peak demand, no margin for error, and every fault turning straight into production standing still.
A mini grid,
steered as one system.
Running off grid
the generator as a last resort.
The hall runs day and night on its own energy. Solar gets used to the maximum and the generators only start when they are genuinely needed. Control sits locally on the gateway, so the site keeps running if the 4G connection drops. Alarms are matched to impact: an email for a small deviation, a text for something bigger, a phone call when it is critical. No panic, and no unnecessary drives out.
Your partner in energy management
Trusted by leading companies for energy flexibility, we bring expertise and experience for demanding energy experts.